Dear all,
We will need to work out what impact this is likely to have on our runners. Although none of them are located in R3 the network server is and we've found we've been unable to remotely access the physical runners and the Windows runners.
I think the safest option might be to put Jenkins into shutdown at 3:30pm that day (a Thursday) to hopefully allow jobs to finish before the power outage starts. We can then put Jenkins back on the following morning once we're sure it's all working again.
It will affect our ORNL colleagues most but it can't be helped.
Thanks
Sarah
From: Wiltshire, Andrew (STFC,RAL,COO) <andrew.wiltshire(a)stfc.ac.uk>
Sent: 26 July 2024 10:57
To: R3 Staff <RAL_R_3_Staff(a)stfc.ac.uk>; Digital Infrastructure (IT) Service Desk <diservicedesk(a)stfc.ac.uk>
Cc: Estate-Helpdesk (RAL) <RALhelpdesk(a)stfc.ac.uk>; Bartram, Richard (STFC,RAL,COO) <richard.bartram(a)stfc.ac.uk>
Subject: Re: Planned Power Outage - 22nd August 5PM
Good morning all,
I realised I forgot to mention that R3 will have no power for the duration of the works.
Kind Regards,
Andrew
Andrew Wiltshire EngTech TMIET
Co-ordinating Authorised Person (Electrical)
Estates Services
Science and Technology Facilities Council
Mobile: 07833 294645
Web: stfc.ukri.org<http://stfc.ukri.org/>
[UKRI_STF_Council-Logo_Horiz-RGB]
STFC is part of UK Research and Innovation www.ukri.org<http://www.ukri.org/>
For more information visit stfc.ukri.or<http://www.stfc.ukri.org/>g
________________________________
From: Wiltshire, Andrew (STFC,RAL,COO)
Sent: 26 July 2024 10:50
To: R3 Staff <RAL_R_3_Staff(a)stfc.ac.uk<mailto:RAL_R_3_Staff@stfc.ac.uk>>; Digital Infrastructure (IT) Service Desk <diservicedesk(a)stfc.ac.uk<mailto:diservicedesk@stfc.ac.uk>>
Cc: Estate-Helpdesk (RAL) <RALhelpdesk(a)stfc.ac.uk<mailto:RALhelpdesk@stfc.ac.uk>>; Bartram, Richard (STFC,RAL,COO) <richard.bartram(a)stfc.ac.uk<mailto:richard.bartram@stfc.ac.uk>>
Subject: Planned Power Outage - 22nd August 5PM
Good Morning,
I am writing to inform you that Estates are planning a planned power outage on August 22nd at 5PM for approximately 2 hours.
This is to carry out Fixed Wire Testing remedial works. Estates will ensure that all systems are fully operational after the works have been carried out.
Can you please reply if there are any issues.
Estates Helpdesk will send out official communications in due course.
Kind Regards,
Andrew
Andrew Wiltshire EngTech TMIET
Co-ordinating Authorised Person (Electrical)
Estates Services
Science and Technology Facilities Council
Mobile: 07833 294645
Web: stfc.ukri.org<http://stfc.ukri.org/>
[UKRI_STF_Council-Logo_Horiz-RGB]
STFC is part of UK Research and Innovation www.ukri.org<http://www.ukri.org/>
For more information visit stfc.ukri.or<http://www.stfc.ukri.org/>g